Overall cost: £240,000.00
Project Brief:
Jennor UK were tasked with the following works:-
We commenced by completely gutting the two suites and the staff area separating the two rooms.
Installed new suspended ceilings throughout inc. new LED lighting panels and emergency fitments.
Supply and installed new Door Casings finished off with the supply and installation of solid core FD30 Fire Doors in a mixture of Hardwood & Paint Grade.
Installed new ‘Polysafe’ Standard PUR flooring throughout the whole of the classrooms following the laying of a new Latex Screed.
Large selection of new Kitchen Wall and Base Units complete with drainage sink basins throughout the suites.
New A/C System throughout, coupled with a state-of-the-art extraction system.
Repair and redecoration of existing Metal Window frames We punched a hole in the external wall to the second floor IT room to form a new external access doorway.
Supply and installation of all new White Goods i.e. Hobs & Ovens, and High backed Student Stools.
Installed a large amount of desktop PowerPoints.
Supplied and installed 5 No. tall fridge freezer ‘Blast Chillers’.
The installation of a new Window Blinds.
Installation of specialist 6 tiered Metal Shelving.
Final Decoration throughout the two suites and adjoining Staff area.
We also carried out a number of repairs to the roof (replaced 4 No. Cowl roof lights) area directly above these two newly remodelling rooms and installed a core drilled fixed galvanised steel handrail to the perimeter of this roof to accommodate the roof works and for future use.
The Result
From four stripped out bland & bare walls into a state of the art Food Technology suite, the transformation has been nothing short of miraculous, which has received plaudits from all involved the ‘Stakeholders’, even the Pupils couldn’t wait to get started!
So here’s to the future and the hope that we’ve placed a few hopeful students on their way to a Michelin Star!
What the client had to say:
Jennor (UK) Ltd completed internal refurbishment and roofing works at Sandbach High School as
acting Principal Contractor.
The works involved both out of hours working and works while the school was in occupation, in
conjunction with the careful management of such activities in order to negate risks.
I can confirm Jennor successfully completed the project, on programme, to a high standard and
managed risks to school occupants at all times.
I would be happy to put Jennor (UK) Ltd forward on future projects within the Education Sector.
Deborah Brown
Associate
For and on behalf of Tuffin Ferraby Taylor LLP